Dedham Square Improvement Project Update, June 3

Here's this week's Dedham Square Project update.

 

According to Dedham Square contractors, they will be repairing the sidewalks that were damaged from this past winter's snow and ice operations.

As a result, two to three on-street parking spaces may not be available during work hours, from 7 a.m. to 5 p.m.

Find out what's happening in Dedhamwith free, real-time updates from Patch.

NSTAR Gas will also continue to replace their utility services on Washington Street and Harris Street.  This is work is not a part of the Dedham Square Improvement Project. If residents need additional information, they can contact NSTAR Gas at 617-424-2697.

Night work will also be conducted from tonight through Thursday from 7 p.m. to 5 a.m.

Find out what's happening in Dedhamwith free, real-time updates from Patch.

According to contractors, there will be full depth reconstruction on High Street, from Court Street to Washington Street.

All residents are asked to move their vehicles from the work area by 6 p.m.  And vehicle not moved will be towed at owners expense.  The contractors will also place signs up in the area during the day.